Statutory Notice & Time-Bar Clocks
In modern construction contracts, failure to issue a written notice of delay within strict statutory timeframes permanently extinguishes your legal right to additional time and prolongation costs. Forge automatically enforces contractual notice countdowns to eliminate condition-precedent forfeitures.
Standard Contractual Time-Bar Windows
28-Day Strict Time-Bar Window
Contractor must give notice of any event or circumstance within 28 days after becoming aware. Failure to give notice relieves the Employer of all liability.
8-Week Compensation Event Notice
If the Contractor fails to notify a compensation event within eight weeks of becoming aware, the Prices, Completion Date, or Key Dates are not changed.
21-Day Claims Window
Claims by either party must be initiated within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition.
"Forthwith" Notice Standard
Contractor must give written notice forthwith upon it becoming reasonably apparent that the progress of the Works is being or is likely to be delayed.
Automated Entitlement Protection
The moment a delay signal is extracted from meeting minutes, daily logs, or RFIs, Forge establishes the baseline event timestamp.
Active countdown badges (e.g. ⚠️ 14 days remaining under FIDIC 20.1) appear in Daily Triage and Claims Defense dashboards, escalating to red when approaching expiry.
Generate formal, contractual notice letters citing exact clause numbers, event descriptions, affected CPM activity IDs, and legal reservations of rights in seconds.